Evaluation item | Observance of the project plan |
Metric | <Post metric #2-2> Observance of project period |
Explanation | Verify compliance with the duration of the project plan in the ex-project (budget) evaluation stage. |
Measurement method | □Did one finish the project according to the project period in the project plan? No--------------Partial--------------Yes ► “Yes” criterion a. When one followed the period of the project plan b. Even if the project is completed early, it is judged as “Yes”► “Partial” criterionWhen the project period is delayed by less than 5% (less than 5% delay)► “No” criterionWhen the project period is delayed by more than 5% (more than 5% delay) |
Data gathering method | □System ■Data □Questionnaires □Interview |
Data sources | Project Plan, Project Closure Report |