Table 4. <Post-implementation metric #2-2> Observance of project period

Item Description
Evaluation item Observance of the project plan
Metric <Post metric #2-2> Observance of project period
Explanation Verify compliance with the duration of the project plan in the ex-project (budget) evaluation stage.
Measurement method □Did one finish the project according to the project period in the project plan? No--------------Partial--------------Yes ► “Yes” criterion a. When one followed the period of the project plan b. Even if the project is completed early, it is judged as “Yes”► “Partial” criterionWhen the project period is delayed by less than 5% (less than 5% delay)► “No” criterionWhen the project period is delayed by more than 5% (more than 5% delay)
Data gathering method □System ■Data □Questionnaires □Interview
Data sources Project Plan, Project Closure Report